Blockwork cost per m², built up properly
The record
- Checked by
- Carl Winson
- Built from
- CIJC Working Rule Agreement
- Wage date
- 20 July 2026
- Grades
- craft rate and general operative
The working
- 2 × tradesperson at £16.40
- £32.80
- 1 × labourer at £13.18
- £13.18
- Gang wage, per hour
- £45.98
- + 35% on top of wages
- £62.07
- × 8 hours on the tools
- £496.58 a day
- 100mm skin10 blocks to the m²£496.58 ÷ 25 m² × 1.20 = £23.84/m²
Benchmark
£23.84/m² labour
CIJC rates · tradesperson £16.40/hr + labourer £13.18/hr · gang of 2+1 · 35% on top · overheads and profit 20%
Materials, scaffold and supervision are not included in this rate.
What’s in this?
- Employer's National Insurance - 15% above £5,000 a year
- Holiday pay - 12.07%
- Pension, auto-enrolment minimum - 3%
- CITB levy - 0.35% of payroll
- Sick pay, training and employer's liability insurance - the remainder
- At 0% this is a CIS subcontractor's labour price - National Insurance, holiday and pension are then theirs to carry, not the job's.
The location range is authored, not measured - our tender data says what was bought where, not what labour costs there.
Price a whole job with this ratePut in the job size and your lump sums - scaffold, plant, skip, and get the job total.
The minimum starts at a day of the gang, priced - £595.90 - because travel, unloading and setting up make a day the honest floor. Type your own, or 0 for none.
Put a job size in and the total appears here.
Six times fewer units, but only half again the speed
A square metre of 100mm blockwork is ten blocks. The same square metre in facing brick is sixty. You would expect blockwork to be six times quicker, and it is not - the benchmark is 25 m² a day for the gang against 16.7 for brick, about half again.
The reason is weight and reach. A brick is a one-handed unit; a dense concrete block is a two-handed lift that has to be placed accurately, and the mortar bed is bigger. Fewer units does not mean proportionally less work when each unit is twenty times the mass.
Which block you are laying changes the day materially
- Dense concrete. Heavy, strong, and the slowest to lay. A 100mm dense block is around 20kg, and manual handling limits are a genuine constraint on a full day of them, not a formality - gangs slow down in the afternoon for a reason.
- Aircrete. Much lighter, cuts with a saw, and considerably quicker to lay. If your job is aircrete, push the output up.
- Thin joint systems. A different method with a different mortar and different output again - quicker in production, but with setting-out demands that punish an inaccurate first course.
- Solid or hollow. Fill and reinforcement change both the handling and the sequence.
One card, one slider: put the output where your block puts it.
The things that slow a blockwork gang
Blockwork looks like the simplest masonry there is, and on a long straight internal wall it very nearly is. What costs time is everything that interrupts the run:
- Openings. Doors and windows mean lintels, closing cavities, and cutting, and the square metres go down while the hours do not.
- Cavity work. Wall ties at centres, insulation boards, cavity trays and keeping the cavity clean is a second discipline running alongside the laying.
- Restraint and reinforcement. Wind posts, bed joint reinforcement and restraint straps to the frame are all slow, fiddly and non-negotiable.
- Cutting. A wall that does not work out to whole blocks vertically is a cut course, and cut blocks are heavy, dusty and slow.
Pricing blockwork on a real job
The gang is two tradespeople and a labourer for the same reason as brickwork: one labourer keeps two people in blocks and mortar and no more, and blocks are heavier to move than bricks. Leaving the labourer out of the price is the same third-of-the-labour error it is on brick, and it is easier to make here because blockwork “feels” like simpler work.
Blocks, mortar, ties, insulation and lintels are materials. Scaffold, once you are above a lift, is a lump sum in the job section - priced by lift and elevation, never by wall area.
Questions people ask
How many blocks are there in a square metre?
Ten, for standard UK concrete blocks with a 440 × 215mm face and 10mm mortar joints, giving a 450 × 225mm coordinating size. That is geometry rather than an estimate, and it holds for dense concrete, aircrete and most lightweight blocks of the same format.
How much blockwork can a gang lay in a day?
Around 25 m² a day for two tradespeople and a labourer laying a 100mm skin, against about 16.7 m² for facing brickwork. Aircrete is quicker than dense concrete because the blocks are far lighter; openings, cavity work, restraint and cutting all pull the figure down.
Why isn't blockwork six times faster than brickwork?
Because the units are heavier as well as bigger. A square metre is ten blocks against sixty bricks, but a dense 100mm block is around 20kg and a two-handed lift, while a brick is a one-handed unit. Fewer, heavier units means about half again the output rather than six times.
Does blockwork include the insulation and cavity work?
The laying rate assumes normal cavity discipline - ties, keeping the cavity clean, but insulation boards, cavity trays, lintels and wind posts are materials and, where substantial, separate work. Anything that interrupts the run costs time, so set the output to reflect the wall you are actually building.
Should a blockwork price include a labourer?
Yes, and leaving one out is the commonest structural error in a self-priced masonry quote. One labourer keeps two tradespeople in blocks and mortar and no more, and blocks are heavier to move than bricks. Pricing the tradespeople alone understates the labour by roughly a third.
Where these figures come from
The wages are the national minimums agreed between employers and unions, republished each July. The costs on top of them are the statutory ones every employer actually pays. The outputs - how much a gang gets through in a day - are blended from published estimating guidance, and they are the part worth arguing with, which is why every one is a control you can move.
Other trades
- Bricklaying£35.68/m²
- Plastering£8.50/m²
- Rendering£38.34/m²
- Floor screed£2.83/m²
- Concreting£7.92/m²
- Tiling£17.71/m²
- Roofing£32.80/m²
- Block paving£25.56/m²
- Tarmac driveways£15.34/m²
- Resin driveways£16.61/m²
- Painting£14.17/m²
- Stud walls£17.71/m²
- Patios£31.95/m²
- Repointing£26.57/m²
- Plasterboarding£12.39/m²
- Decking£31.88/m²
- Fencing£25.56/m²
- Turfing£3.42/m²
- Coving£7.08/m²
- Loft insulation£4.27/m²
- External wall insulation£38.34/m²
- Soft strip£8.54/m²
- Hand excavation£85.41/m²
- Shuttering£8.50/m²
- Mesh and rebar£2.56/m²
Pricing a job like these?
HubTrack is where small construction firms keep their compliance documents, their jobs and their evidence trail in one place - method statements and risk assessments prepared for you to check and sign off, and a record of who signed what and when. The same engine that reads the contract documents behind this page reads yours inside HubTrack.