Calculator
Bricklaying cost per m², built up properly
The record
- Checked by
- Carl Winson
- Built from
- CIJC Working Rule Agreement
- Wage date
- 20 July 2026
- Grades
- craft rate and general operative
The working
- 2 × tradesperson at £16.40
- £32.80
- 1 × labourer at £13.18
- £13.18
- Gang wage, per hour
- £45.98
- + 35% on top of wages
- £62.07
- × 8 hours on the tools
- £496.58 a day
- Half-brick facing wall60 bricks to the m² - 1,000 bricks a day for the gang£496.58 ÷ 16.7 m² × 1.20 = £35.68/m²
Benchmark
£35.68/m² labour
CIJC rates · tradesperson £16.40/hr + labourer £13.18/hr · gang of 2+1 · 35% on top · overheads and profit 20%
Materials, scaffold and supervision are not included in this rate.
What’s in this?
- Employer's National Insurance - 15% above £5,000 a year
- Holiday pay - 12.07%
- Pension, auto-enrolment minimum - 3%
- CITB levy - 0.35% of payroll
- Sick pay, training and employer's liability insurance - the remainder
- At 0% this is a CIS subcontractor's labour price - National Insurance, holiday and pension are then theirs to carry, not the job's.
The location range is authored, not measured - our tender data says what was bought where, not what labour costs there.
Price a whole job with this ratePut in the job size and your lump sums - scaffold, plant, skip, and get the job total.
The minimum starts at a day of the gang, priced - £595.90 - because travel, unloading and setting up make a day the honest floor. Type your own, or 0 for none.
Put a job size in and the total appears here.
What a bricklaying rate covers, and what it does not
The rate above is labour only - the gang’s time to lay the brickwork, and nothing else. On facing brickwork that is usually the smaller half of the price: at sixty bricks to the square metre, materials at 60p to 90p a brick put £36 to £54 of brick alone against roughly £36 of labour, before mortar, wall ties, insulation or cavity trays.
Scaffold sits outside it too, and deliberately. Scaffold is priced by lift and elevation, not by wall area, so folding it into a per-square-metre figure produces something that looks precise and is wrong on every job that is not the shape you assumed. Price it as a lump sum in the job section, the way you would on a real quote.
Why the labourer is in the gang, and what happens if you leave them out
A bricklaying gang is two bricklayers to one labourer because one labourer keeps two trowels going in mortar, brick and ties, and no more. Price the bricklayers alone and the rate lands around £15.74 a square metre instead of £22.05 - you have just given away nearly a third of the labour, and it is a third that shows up as an unpaid person on site every day of the job.
It is the commonest structural error in a self-priced brickwork quote, and it is invisible until the job is running, because the arithmetic is perfectly correct - it simply prices the wrong number of people.
What actually changes the price on a real job
Output, how many bricks a day get laid, moves the rate one for one, and almost everything else on a job moves output. These are the ones worth reaching for the slider over:
- Bond. Straightforward stretcher bond runs around 500 bricks a day. Flemish bond, English bond or anything decorative drops that to nearer 300 - a forty per cent swing in the labour, and the single biggest thing missed when a quote is put together from a remembered rate.
- Openings and detail. A wall with windows, reveals, cills and arches is cutting and setting out rather than laying. The square metres go down and the hours do not.
- Height and scaffold lifts. Every lift costs most of a day of stop-start while the scaffold moves, and it is a fixed cost against a smaller area on a small job.
- Weather. Brickwork stops below about 3°C and stops in driving rain. A winter programme is not a slower programme so much as an interrupted one.
- Repetition. Long straight runs are the fastest brickwork there is. A gang that is on the same detail all week gets quicker; a gang moving between piers, returns and features never does.
If your job is Flemish bond with a lot of openings, drag the output down to eight or nine square metres a day and watch the rate. That is what the job is actually worth, and the reason we put the control on the page rather than choosing for you.
Pricing brickwork for a tender rather than a quote
Two things change when the price is going into a tender rather than to a private client. Preliminaries stop being your problem and start being priced separately - welfare, scaffold, plant, supervision usually sit in the main contractor’s preliminaries rather than in your unit rate, so a rate that quietly carries them is a rate that loses.
And the rate is compared line by line against other people’s. That is where a build-up earns its keep: when a quantity surveyor asks how you got to your figure, “a gang of two and a labourer at published rates, 500 bricks a day” is an answer. A number you remembered from the last job is not.
Working out a whole brickwork job
Open the job section on the calculator and put the wall area in: the rate spreads across it, your scaffold and skip go on as lump sums, and the minimum charge holds the floor if the job is smaller than a day. Sixty square metres of facing brickwork with a £2,000 scaffold and a £300 skip comes out around £4,441 of labour and lump sums - with the bricks, mortar and ties still to add.
If you price work like this every week, that is the job HubTrack does: your gang and your rates remembered, applied across a whole job, with the paperwork the tender asks for kept alongside it rather than in a different folder.
Questions people ask
How many bricks are there in a square metre?
Sixty, for a half-brick (single skin) wall in standard UK metric bricks with 10mm joints. That is geometry rather than an estimate: a brick with its joints presents 225mm by 75mm, so a square metre takes 59.3 of them. The figure has not changed since metric brick sizes were standardised in the 1970s.
How many bricks can a bricklayer lay in a day?
Around 500 a day in straightforward stretcher bond, with 400 to 600 the normal range depending on access, weather and complexity. Decorative work - Flemish or English bond, curved walls, heritage repair - drops it to between 250 and 350.
What is a realistic labour rate per square metre for brickwork?
Around £22 a square metre in wage cost for a gang of two bricklayers and a labourer at national agreed rates, or roughly £36 once overheads and profit are added. Published cost guides put bricklaying labour at £35 to £55 a square metre, so a build-up from published wages lands inside that range rather than arguing with it.
Does a bricklaying price include materials?
Not in our rate, no - it is labour only. Materials are typically the larger half of a facing brickwork price: sixty bricks per square metre at 60p to 90p each, plus mortar, wall ties and any insulation or cavity trays.
Why is one bricklaying quote so much higher than another?
Usually because the two are pricing different amounts of work per day rather than different hourly rates. Wages are set nationally and barely vary; output varies enormously with bond, openings, access, height and weather. A gang assuming 500 bricks a day and one assuming 350 will differ by about 40% on identical wages.
Should a bricklayer's price include scaffold?
Normally not on tendered work, where scaffold usually sits in the main contractor's preliminaries. Scaffold is priced by lift and elevation rather than by wall area, so carrying it inside a per-square-metre rate makes the rate wrong on any job that is not the shape you assumed.
Where these figures come from
The wages are the national minimums agreed between employers and unions, republished each July. The costs on top of them are the statutory ones every employer actually pays. The outputs - how much a gang gets through in a day - are blended from published estimating guidance, and they are the part worth arguing with, which is why every one is a control you can move.
Other trades
- Blockwork£23.84/m²
- Plastering£8.50/m²
- Rendering£38.34/m²
- Floor screed£2.83/m²
- Concreting£7.92/m²
- Tiling£17.71/m²
- Roofing£32.80/m²
- Block paving£25.56/m²
- Tarmac driveways£15.34/m²
- Resin driveways£16.61/m²
- Painting£14.17/m²
- Stud walls£17.71/m²
- Patios£31.95/m²
- Repointing£26.57/m²
- Plasterboarding£12.39/m²
- Decking£31.88/m²
- Fencing£25.56/m²
- Turfing£3.42/m²
- Coving£7.08/m²
- Loft insulation£4.27/m²
- External wall insulation£38.34/m²
- Soft strip£8.54/m²
- Hand excavation£85.41/m²
- Shuttering£8.50/m²
- Mesh and rebar£2.56/m²
Pricing a job like these?
HubTrack is where small construction firms keep their compliance documents, their jobs and their evidence trail in one place - method statements and risk assessments prepared for you to check and sign off, and a record of who signed what and when. The same engine that reads the contract documents behind this page reads yours inside HubTrack.