Tarmac driveways cost per m², built up properly

Start from the benchmark - published wages, a real gang, the costs on top of wages most people forget - then move anything you disagree with. The whole sum stays on the page.

The record

Checked by
Carl Winson
Built from
CIJC Working Rule Agreement
Wage date
20 July 2026
Grades
craft rate and general operative

The working

2 × tradesperson at £16.40
£32.80
2 × labourer at £13.18
£26.36
Gang wage, per hour
£59.16
+ 35% on top of wages
£79.87
× 8 hours on the tools
£638.93 a day
  • Base coursebinder laid and rolled on a prepared sub-base£638.93 ÷ 100 × 1.20 = £7.67/
  • Wearing coursetop course laid to falls and rolled£638.93 ÷ 100 × 1.20 = £7.67/

Benchmark

£15.34/m² labour

CIJC rates · tradesperson £16.40/hr + labourer £13.18/hr · gang of 2+2 · 35% on top · overheads and profit 20%

Materials, scaffold and supervision are not included in this rate.

The gangTradesperson2Labourer2
What’s in this?
  • Employer's National Insurance - 15% above £5,000 a year
  • Holiday pay - 12.07%
  • Pension, auto-enrolment minimum - 3%
  • CITB levy - 0.35% of payroll
  • Sick pay, training and employer's liability insurance - the remainder
  • At 0% this is a CIS subcontractor's labour price - National Insurance, holiday and pension are then theirs to carry, not the job's.

The location range is authored, not measured - our tender data says what was bought where, not what labour costs there.

Price a whole job with this ratePut in the job size and your lump sums - scaffold, plant, skip, and get the job total.

The minimum starts at a day of the gang, priced - £766.71 - because travel, unloading and setting up make a day the honest floor. Type your own, or 0 for none.

Put a job size in and the total appears here.

The gang is racing a temperature, not a clock

Hot-laid tarmac arrives at around 140°C and has to be spread and rolled before it drops below roughly 105°C. In practice that is a 30 to 45 minute window from the lorry tipping to the roller finishing, and less on a cold or windy day. Compact it too late and the surface never reaches density - it looks fine, and it ravels within two winters.

That is why a tarmac gang is four hands rather than two, and why it prices a day rather than an hour. You cannot pause a load, and a load that goes cold on the wagon is scrap you have paid for.

Why base course and wearing course are separate operations

They are two different materials at two different depths doing two different jobs. The base course carries the load and takes up the level; the wearing course is the finish and is thinner, finer and more expensive. Both go through the same laying and rolling, so each is roughly 100 m² a day for the gang.

Plenty of jobs are only one of them. An overlay on a sound existing surface is wearing course alone. A car park built up from a fresh sub-base is both, on separate days. Slide the one you are not doing to zero rather than halving a combined rate and hoping.

Joints are where tarmac fails, and they cost time

Every joint - between loads, between days, against an existing surface, around an ironwork cover - is a potential weak line. Done properly they are cut back, tacked and rolled through; done in a hurry they open up and let water in, and water is what finishes a driveway.

  • Access for the wagon and roller. A drive the roller cannot get onto is hand-tamped, and hand-tamped tarmac is a fraction of the output and never as dense.
  • Shape. Long straight runs are quick. Narrow drives, tight radii and edges against a garage threshold are all hand work at the exact moment the material is cooling.
  • Ironwork. Manholes, gullies and stop taps each need cutting round and finishing by hand.
  • Weather. Below about 10°C ambient the window shortens sharply; in rain you do not lay at all, because water trapped under the mat is a delamination waiting to happen.

What is not in this rate

The sub-base. On a new driveway the dig, the muck away and the Type 1 laid and compacted are usually more work than the surfacing, and they are priced on the excavation and sub-base calculators. Kerbs and edgings are separate too.

The tarmac itself is a material, and the roller and whacker are plant - both go in the job section as lump sums, alongside the skips if you are carrying the dig.

Questions people ask

What temperature does tarmac need to be laid at?

Hot-laid tarmac arrives at around 140°C and must be compacted before it falls to roughly 105°C, which gives about 30 to 45 minutes from tipping to finished rolling. Ambient conditions matter too: below about 10°C the window shortens sharply, and tarmac should not be laid in rain because trapped water causes delamination later.

How much tarmac can a gang lay in a day?

Around 100 m² of a single course a day for a four-hand gang with a roller, on reasonable access. A full base course and wearing course on the same area is therefore two operations' worth of days, not one.

Do you need both a base course and a wearing course?

Not always. An overlay onto a sound existing surface is wearing course only. A new driveway or car park built from a fresh sub-base needs both - the base course carries the load and takes up level, the wearing course is the finish. They are separate operations on the calculator so you can price only the one you are doing.

Why do tarmac driveways crack or ravel after a couple of years?

Usually inadequate compaction or a poor joint rather than the material itself. Tarmac that was rolled after it dropped below temperature never reaches density, and joints that were not cut back and tacked let water in. The sub-base is the other common cause - tarmac takes the shape of what is under it.

Does a tarmac price include the sub-base?

Not in this rate. This covers laying and rolling the tarmac itself. Excavation, muck away, and Type 1 sub-base laid and compacted are separate work, often more than the surfacing on a new driveway, and are priced on their own calculators.

Where these figures come from

The wages are the national minimums agreed between employers and unions, republished each July. The costs on top of them are the statutory ones every employer actually pays. The outputs - how much a gang gets through in a day - are blended from published estimating guidance, and they are the part worth arguing with, which is why every one is a control you can move.

The full method, step by step →

Pricing a job like these?

HubTrack is where small construction firms keep their compliance documents, their jobs and their evidence trail in one place - method statements and risk assessments prepared for you to check and sign off, and a record of who signed what and when. The same engine that reads the contract documents behind this page reads yours inside HubTrack.