What roads, utilities and groundworks work sells for

Read from 537 UK public contract awards. Every figure below states how many jobs are behind it.

What it went for

£220,000

the middle of 537 awards, from £1,289 to £23,455,545

Half of all roads, utilities and groundworks awards fell between £76,365 and £919,090.

£1,289The scale steps by tens, so the smallest job and the largest both fit on it.£23,455,545

Against the estimate

Awarded at the estimate.

40% underthe advertised estimate40% over

62 of these jobs advertised an estimate before bids came in

How long the decision takes

112 days from advert to award. About the middle for construction work — the all-trades middle is 112 days.

0 days150 days

the middle of 71 jobs whose advert and award were both published

When roads & groundworks work comes out to bid

October is the busiest month and May the quietest — 135 against 42, across 5 full years.

  1. January: 98 advertised
  2. February: 83 advertised
  3. March: 53 advertised
  4. April: 57 advertised
  5. May: 42 advertised
  6. June: 65 advertised
  7. July: 69 advertised
  8. August: 90 advertised
  9. September: 120 advertised
  10. October: 135 advertised
  11. November: 126 advertised
  12. December: 114 advertised

counted on tenders advertised, which is what a contractor plans around — a month with nothing held is shown as a dash, never a zero

Where these figures come from

Every figure is read from contract award notices published by UK public bodies — councils, NHS trusts, housing associations, government departments — under the Open Government Licence. Nothing is estimated, modelled or filled in. A figure appears only once enough awards support it, and it always states how many.

The figures are rebuilt each night, last on 6 August 2026. They cover publicly tendered work, which is not the same as domestic or private commercial work: a price here is what a public body paid a contractor on a contract that went through a formal tender.

Pricing a job like these?

HubTrack is where small construction firms keep their compliance documents, their jobs and their evidence trail in one place — method statements and risk assessments prepared for you to check and sign off, and a record of who signed what and when. The same engine that reads the contract documents behind this page reads yours inside HubTrack.